Toll Booth construction update: Week 6

November 17, 2017
By Marcy Shortuse
Contract Duration: 90 days from permit issue date of 9/29/17 The stucco subcontractor has been on site all week. Next week the metal roofs will be installed, and the toll plaza will be painted the following week. During active construction hours Monday-Friday, two on-island traffic lanes will remain open with the exception of material deliveries […]