Here’s a look at the newest timeline provided by Steele Construction, Inc. as to when the tower might be up. Now that the bakery is gone things should move quickly, but this schedule is an optimist’s look at what could happen … if everything goes right.

Here’s a look at the newest timeline provided by Steele Construction, Inc. as to when the tower might be up. Now that the bakery is gone things should move quickly, but this schedule is an optimist’s look at what could happen … if everything goes right.

September 5: Steele team gets here and semi trucks get loaded.

September 6: Steel plates to protect the street will be delivered and a DOT road closure will be put in place.

September 7: “Frac” tanks will be delivered, and the water hauler will fill them.

September 8: Semis will deliver equipment, and they will start “tying” the foundation steel.

September 9: More tying of foundation, drill will be offloaded.

September 10: Team will set the casing and mix the necessary additives.

September 11 – 13: Finish up and pour concrete for monopole base.

September 19: Tower might be up? Depends on the weather and whatever other factors the fates throw our way.