tos_2570Ajax Paving Industries of Florida, LLC is moving right along with road paving and widening, and this past week they started putting some shoulders on Gasparilla Road.

According to Project Manager Scott Gilliard, crews will be on Gasparilla Road all next week working, and lane closures will be happening each day. Any homeowners who live right on the Gasparilla Road easement should be mindful of the fact that all sprinkler heads in the path of the project have been capped. Some bushes have been cut as well.

Paving downtown is done, Gilliard said, but there is a little work on some Gulf Boulevard turnouts that the crew will come back and do later.

The bike path work is complete, as is all work planned on Gulf Boulevard.

Please plan accordingly for road delays, and use patience while driving.